The Interceptor, Warren, and the Red Run

April 1, 2012

WasteWater treatment plants – and – StormWater Retention basins
are 2 very separate things.

The Red Run is a StormWater drain operating off of the Kuhn Retention Basin.

The Oakland Macomb Interceptor is a 12-foot 9-inch diameter pipe
for transporting sewage from houses and commercial buildings to
Detroit Water and Sewage Department for treatment and disposal.

A 53-foot diameter access shaft in Warren is located in the ITC corridor
north of Common Road between Schoenherr and Hoover.

Interceptor Pipe and Access Shaft

Interceptor Pipe and Access Shaft

Former mayor of Warren, Mark Steenbergh works now for the massive sewer division servicing 11 Macomb County communities.

The Oakland Macomb Interceptor (OMI) Project is over 21 miles long
and services 830,000 residents living in 24 communities.
The estimated project cost of the repairs is $200,000,000 taking
approximately 5 years and is financed through the
Michigan Water Pollution Control Revolving Fund.

A slideshow of some work done can be seen here:
http://www.mancinicompanies.com/featured-projects/oakland-macomb-interceptor-drain

~~~~ click on pic for enlarged image ~~~~~

Interceptor projects Overall View

Interceptor projects Overall View

Construction of the first phase which began in February of 2010, is now complete.
It involved five new permanent flow control / access structures .
This provide a means of controlling flow in the system by using the upstream pipes for temporary storage while work continues on the lower sections.

~~~~ click on pic for enlarged image ~~~~~

Interceptor Construction Staging Areas

Interceptor Construction Staging Areas

Design for the second phase of the project has been completed.
Construction is expected to begin by January of 2012.
Rehabilitation of the pipe in the lower half of the OMI system will begin with this phase,
This phase of the work is scheduled to take approximately two years.

~~~~ click on pic for enlarged image ~~~~~

Interceptor Project Schedule

Interceptor Project Schedule

Design efforts also began on the third phase.
Construction of phase three is expected to overlap with phase two
and is expected to begin in 2013.

~~~~ click on pic for enlarged image ~~~~~

Interceptors Oakland Macomb Michigan

Interceptors Oakland Macomb Michigan

Oakland County Interceptor draining into Macomb County

Oakland County Interceptor draining into Macomb County

Oakland Macomb Interceptor

Oakland Macomb Interceptor

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: