OAKLAND – MACOMB INTERCEPTOR DRAIN
(OMID) REHABILITATION PROJECT

Project Management Plan for Contract 4

The entire report can be seen here (released August 20, 2013)
http://www.oakgov.com/water/Documents/omi_final/Legal/082013%20Macomb%20Project%20Plan.pdf

The split of OMID repair costs between Macomb and Oakland Counties
– is 51.5% and 48.5%, respectively.

In addition, of the total volume measured at the Northeast Sewage
Pumping Station (NESPS), which serves as the terminus of the OMID
to Detroit’s North Interceptor-East Arm (NI-EA), and billed to OMID,
– Macomb County assumes 60% while Oakland County assumes only 40%.

The Wastewater Services contracts between the OMIDDD and Macomb County
and OMIDDD and Oakland County provides that for the first three years,
the operations and maintenance costs are to be allocated
51.5% and 48.5% between Macomb and Oakland Counties, respectively.

Contract 4 is a continuation of the overall program for the rehabilitation
of the Oakland-Macomb Interceptor Drain (OMID), which consists of the
Edison Corridor Interceptor (PCI- 5, 6, and 7),
the Oakland Arm Interceptor (PCI-8, 9, 10A, and 10B),
and the Avon Arm Interceptor (PCI-11A) which is a tributary.
https://redrundrain.files.wordpress.com/2013/08/omid-control-structure-map.jpg

The work is anticipated to take up to two (2) years from the
Notice-to-Proceed date (August 7, 2013) as the
target substantial completion.
date is August 6, 2015.

Mark Steenbergh the OMID Community Services Manager
– Currently sits on the wastewater rates look-back,
wastewater rates simplification committee,
wastewater flow balance task force group subcommittee.
– Attends monthly Board of Water Commissioners (BOWC) meetings.
– Represents Macomb Public Works on pollution control projects
a.) PC-791 – a $38 million incinerator rehabilitation
b.) PC-792 – a $146 million construction of bio-solids drying facility.
– Provides oversight for the Macomb Interceptor Drainage District (MID).
– Serves as liaison between the Office of the Macomb County Public Works
and local elected officials, as well as municipal officials responsible
for wastewater services in the Macomb County Wastewater Disposal District .

OMID Control Structure Map

OMID Control Structure Map

Oakland Macomb Interceptor

Oakland Macomb Interceptor

Advertisements
One Comment

Trackbacks & Pingbacks

  1. Upgraded Warren Sewers ? | Red Run

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: